Building By-law 26-50
Schedule A - Classes of Permits and Permit Fees
1) Except where a minimum flat fee is indicated for the Occupancy Classification
or Type of Construction, the fee per ft² of floor area set out in Schedule "A"
shall be used by the Chief Building Official in determining the permit fee.
2) For the purpose of this Schedule the occupancy classification and floor area
shall be determined on the following basis:
a) The occupancy classification shall be established in accordance with the
occupancy definitions of the Ontario Building Code and its appendices.
b) The floor area shall be measured to the outer face of exterior walls and to
the centre line of party walls or demising walls. No deductions shall be
made for openings within the floor area (e.g. stairs and stair openings,
ducts, elevators, escalators). Floor area shall include all habitable areas,
including mezzanines, finished attics and enclosed balconies. The
following shall apply to Part B of Schedule A in determining the fee
payable for a given building type:
-
Assembly Occupancies - The "Assembly Occupancies" rate shall
apply to the total floor area of floors which are principally of assembly
use. Other rates shall be applied to other floors based on the
principal use of the total floor area.
-
Institutional Occupancies - The "Institutional Occupancies" rate
shall apply to the floor areas of floors which are principally of
institutional use. Other rates shall be applied to other floors based on
the principal use of these areas.
-
Residential Occupancies - The "Residential Occupancies" rate shall
apply to the floor areas of floors which are principally of residential
use. Other rates shall be applied to other floors based on the
principal use of the total floor area.
-
Business and Personal Services Occupancies - The applicable
"shell" rate shall be applied to the floor areas of a speculative
structure, where the only finished floor areas are to be the common
areas (e.g. lobby, corridors, washrooms).
The "Interior Partitioning and Finishing" rate shall be applied where
finished floor areas are to be provided in other than common areas.
Other rates shall be applied to other floors based on the principal use
of the total floor area.
-
Mercantile Occupancies -The "Mercantile Occupancies" rate shall
be applied to the floor areas of a speculative structure, where the
only finished floor areas are to be the common areas (e.g. lobby,
corridors, washrooms).
By-law 26-50
Page 2 of 8
The "Interior Partitioning and Finishing" rate shall be applied where
finished floor areas are to be provided in other than common areas.
Other rates shall be applied to other floors based on the principal use
of the total floor area.
-
Industrial Occupancies - Each "Industrial Occupancies" rate
includes incidental finished office space to a maximum of 10% of the
total floor area.
The "Interior Partitioning and Finishing" rate shall be applied where
additional finished space is provided. Other rates shall be applied to
other floors based on the principal use of the total floor area.
3) Where an order to comply, a stop work order or any Order under the
requirements of the Building Code Act (as amended) has been issued with
respect to construction and demolition where works have commenced prior
to issuance of permit, the permit fee prescribed in Schedule 'B' shall be
doubled. Where an Inspector leaves notice on site in regard to construction
and or demolition where work has commenced without the benefit of permit,
the permit fee prescribed in Schedule 'B' shall be doubled.
4) With respect to conditional permits, the fee shall be the fee set out in
Schedule 'B" for the proposed construction.
By-law 26-50
Page 3 of 8
Building By-law 25-50
Schedule B - Building Permit Fee Schedule
Major Occupancy
Base Fee
Adjusted Permit
Fee
Group A, B, D, E, F
1
New Construction
-
Complete building
-
Shell only
$4,624 up to
2,500ft2
$1.84 per ft2 for
floor area over
2,500ft2
2
Major additions or alterations
$3,083 up to
2,500ft2
$1.24 per ft2 for
floor area over
2,500ft2
3
Minor Additions
-
Retrofit
-
Interior finishes
-
Stand alone plumbing
-
Stand alone heating
-
Sprinkler system
-
Portable classroom
$1,079 up to
2,500ft2
$0.43 per ft2 for
floor area over
2,500ft2
Group C
1
Low Density
-
Single detached
-
Semi detached (per unit)
-
Mobile Home
$3,083 up to
2,200ft2
(including attached
garage, covered
porch and finished
basement)
$1.40 per ft2 for
floor area over
2,200ft2 and
attached garage
2
Multiple Residential
-
Townhouse
-
Row dwelling
-
Triplex
-
Quadraplex
-
Apartment
-
All other Group C
occupancies
$3,083 up to
2,200ft2
(including attached
garage, covered
porch and finished
basement)
$1.40 per ft2 for
floor area over
2,200ft2
3
Major Alterations and Additions
$2,159 up to
2,200ft2
(including attached
garage, covered
porch and finished
basement)
$1.40 per ft2 for
floor area over
2,200ft2
By-law 26-50
Page 4 of 8
4
Minor Alterations and Additions
(including covered porches)
(<$50,000 construction value)
$463 up to 300ft2
$1.40 per ft2 for
floor area over
300ft2
Accessory Dwelling Units
1
Located Within a House
$2,090
N/A
2
Addition
$2,090
N/A
3
Detached
$2,090
N/A
Group G - Farm Buildings
1
New, Additions, Alterations,
Accessory Buildings
$463 up to 1579ft2
$0.32 per ft2 for
floor area over
1579ft2
2
Greenhouse (polyethylene film)
$463
N/A
Miscellaneous Work
Base Fee
Adjusted
Permit Fee
1
Accessory Building
-
Detached garage
-
Carport
-
Accessory Building
$494 up to 300ft2
$0.68 per ft2 for
floor area over
300ft2
2
Deck
$193 up to 300ft2
$0.66 per ft2 for
floor area over
300ft2
3
Stand Alone Plumbing
$193
N/A
4
Stand Alone HVAC
$193
N/A
5
Change of Use - to residential
$2,159 up to 2,200ft2
$1.40 per ft2 for
floor area over
2,200ft2
6
Change of Use - to non-
residential (minor)
$1,079 up to 2,500ft2
$0.43 per ft2 for
floor area over
2,500ft2
7
Change of Use - to non-
residential (major)
$3,083 up to 2,500ft2
$1.24 per ft2 for
floor area over
2,500ft2
By-law 26-50
Page 5 of 8
8
Combined Service Connection
-
Water
-
Sanitary/storm sewer
$193
N/A
9
Residential Inground Pool
$193
N/A
10
Residential Above Ground Pool
$116
11
Wood Burning Appliance
$193
N/A
Demolition
1
Single Detached and Two Unit
Dwellings or Farm Building
$193
2
Non-Residential
$2,004
N/A
Sewage Systems
1
New Sewage System
$695
N/A
2
Septic Tank or Repair to Existing
Sewage System
$361
N/A
3
Septic Review Fee
$193
N/A
Designated Structures
1
As Defined Under 1.3.1.1 Div A,
OBC, as amended
-
Retaining Wall
-
Underpinning
-
Tower facility
-
Wind turbines
-
Solar panels
-
Signs
-
Temporary Stages
$463
$18.50 for each
$1000 of
Construction
Value
2
Public Pool or Public Spa
$463
N/A
Temporary Buildings
1
Tents up to 225m2
$937
N/A
2
Tents Greater Than 225m2
$385
N/A
By-law 26-50
Page 6 of 8
Administrative Fees
Fee
Miscellaneous
1
Orders under the Building Code
(per order)
$464
2
Registering Order on Title
$773
3
Discharging Order from Title
$773
4
Administration Fee for Orders
$464
5
Title Search
$464
6
Permit File Retrieval Fee
$193
7
Transfer of Permit Application or
Building Permit or Change of
Ownership
$193
8
Construction Without a Building
Permit
An administrative surcharge of the
greater of $193 or 100% of the permit
fee will apply if construction has
commenced prior to the issuance of the
building permit
Alternative Solutions
1
All buildings/systems under Part
9
$695
2
All other buildings/systems
$2,159
Compliance Letters
1
AGCO Agency Letter
$193
2
Building Permit File Compliance
Letter
$193
3
Private Sewage System
Compliance Letter
$193
4
Occupancy Permit Letter
$193
By-law 26-50
Page 7 of 8
Conditional Building Permits
1
New House
25% surcharge of the base calculated
building permit fee
2
All Other Buildings
25% surcharge of the base calculated
building permit fee
3
Amendments to Conditional
Building Permit Agreements
25% surcharge of the base calculated
building permit fee
Inspection Fees
1
One additional inspection
$155
2
Two or more additional
inspections
$309
Revision to Reviewed Permit Drawings
1
Minor Revision
$193
2
Major Revision up to 3 Hours
$283
3
Major Revision for Each Hour
After 3 Hours of Review Time
$141
Indexing
Building permit fees imposed pursuant to this By-law shall be adjusted annually
without an amendment to this By-law, on January 1st of each year, commencing
January 1st, 2025, in accordance with the prescribed index in the Act based on the
twelve-month period ending September 30th. Notwithstanding the above, indexing
may be altered by by-aw for a one-year period based on the annual financial
reporting of the Building Department and shall be based on the construction index
but will be no more than a 3% increase.
Effective January 1, 2026 to
Indexing
%
December 31, 2026
Suggested C.I. 4.2%
3% max.
By-law 26-50
Page 8 of 8
Building By-law 26-50
Schedule E - Applications and Forms Prescribed by Regulation
under the Building Code Act, as amended and Clearview Township
1) Application for a Permit to Construct or Demolish
2) Application for a Permit to Construct an Onsite Sewage System (Septic)
3) Schedule One Designer Form
4) Schedule Two Designer Form
5) Energy Efficiency Design Summary Form (Residential)
6) Energy Efficiency Design Summary Form (Commercial) and SB10
7) Commitment to General Review
8) Application for an Alternative Solution
9) Ontario Building Code Matrix
10) Declaration Form for Secondary Suites
11) Commercial Roof Water Storage
12) Sewer/Water Connection Permit Form
13) Demolition Permit Declaration Form