In the Township of Huron-Kinloss, Ontario, building permit rules are set by Building By-law No. 2012-41 (Consolidated, amended by 2019-16), verified 2026-09-25. Permit required for: Construction, demolition, change of use, occupancy of a partially complete building, conditional permits and other classes as set forth in Schedule A. Fees set in: Building Fees By-Law as amended. Administered by: Chief Building Official.
Building By-law No. 2012-41 (Consolidated, amended by 2019-16)
adopted bylaw
permit required for
Construction, demolition, change of use, occupancy of a partially complete building, conditional permits and other classes as set forth in Schedule A.
s. 2.1
fees location
Building Fees By-Law as amended
s. 3.1
authority
Chief Building Official
s. 1.2(f)
scout note