| permit required for | No person shall undertake any work unless a permit has been issued by the CBO; work means construction or demolition of a building or part thereof including changes of use. | s. 3.1; s. 2.37 |
| fee basis | Calculated per Schedule A: ((TCC/1000) x Rate) + Administrative Fee = Permit Fee; Rate = $10.00; or based on floor area/cost of construction, higher if both. | Schedule "A"; s. 7.1 |
| fees location | Schedule A of this By-Law | s. 7.1; Schedule "A" |
| authority | Chief Building Official (CBO) issues permits; building officials conduct inspections. | s. 2.13; s. 3.1; s. 17.1 |
| fine range | additional administration fee equal to twice the value of the fee applicable under Schedule A or $250, whichever is greater | s. 13.1 |
scout note
Municipality of St.-Charles's Building By-law under s.7 of the Building Code Act 1992: construction/demolition/change-of-use/conditional permits, inspections, fees (Schedule A), and 15-year dormant-file provision. Passed July 2026.