| permit required for | To perform work regulated by this By-law and the Act, or to change the use of a building. | s. 2, definition of 'Permit' |
| fee basis | As set out in Schedule "A"; based on floor area or cost of valuation; minimum fee plus $10/$1,000 of contracted construction value where not accurately assessed per sq ft. | s. 6.1; s. 6.3; s. 6.5; Schedule "A" NOTE |
| authority | Chief Building Official | s. 2, definition of 'Chief Building official' |
scout note
Municipality of West Perth by-law for administration/enforcement of the Building Code Act: permit classes, application documents, inspections, chief building official code of conduct, and its own building permit fee schedule (pp.8-10).